Painting Has Begun

Painting, drywall and electrical work continue on our church campus this week. Below are a few images detailing the progress that has been made.


First coats of paint have been applied to our children's worship space upstairs.



Jeff Daniel has been hard at work on this area. He estimates three to four weeks for his part of the project. This back wall will see screens, staging, lighting, and more over the coming months.



The columns in the hallway of our kids atrium were painted as well. A honeycomb mosaic, new seating, and more will complete this area soon.




Lighter, brigher, and refreshed common areas are part of the overall renovation plan.



Sheetrock and electrical work are continuing in the sanctuary. First coats of paint are expected in two weeks. Stonework, seating, staging, and sceneic elements will be handled by the Paragon installation team after the first of the year.



 
 
 